Active Items
Admin
Price Book
Admin controls for custom waterproofing quote pricing. Keep costs, default prices, and margin assumptions current before building estimates.
Inactive
Categories
Templates
ID-100 | Interior drain tile system
Interior perimeter drain tile with trenching, stone, pipe, and wall flange.
- Category
- Interior drainage
- Unit
- LF - Linear foot
- Cost
- $42.00
- Default Price
- $92.00
- Margin
- 54.35%
- Markup
- 119.05%
- Updated
- Jul 9, 2026
- Internal
- Adjust for finished basement protection and tight access.
EW-100 | Exterior waterproofing system
Exterior excavation, waterproofing membrane, protection board, drain stone, and backfill.
- Category
- Exterior waterproofing
- Unit
- LF - Linear foot
- Cost
- $185.00
- Default Price
- $395.00
- Margin
- 53.16%
- Markup
- 113.51%
- Updated
- Jul 9, 2026
- Internal
- Verify depth, machine access, utilities, and landscape restoration.
SP-100 | Primary sump pump package
Primary sump pump, basin lid, check valve, and standard installation.
- Category
- Sump pumps
- Unit
- EA - Each
- Cost
- $475.00
- Default Price
- $1,250.00
- Margin
- 62.00%
- Markup
- 163.16%
- Updated
- Jul 9, 2026
- Internal
- Electrical outlet must be available or add electrical support.
SP-200 | Battery backup sump package
Battery backup pump package with battery box and alarm.
- Category
- Sump pumps
- Unit
- EA - Each
- Cost
- $685.00
- Default Price
- $1,695.00
- Margin
- 59.59%
- Markup
- 147.45%
- Updated
- Jul 9, 2026
- Internal
- Confirm maintenance expectations with homeowner.
DL-100 | Buried discharge/downspout line
Buried discharge or downspout line with pipe, fittings, and trench backfill.
- Category
- Discharge/downspout lines
- Unit
- LF - Linear foot
- Cost
- $18.00
- Default Price
- $42.00
- Margin
- 57.14%
- Markup
- 133.33%
- Updated
- Jul 9, 2026
- Internal
- Add pop-up emitter or daylight termination as needed.
CR-100 | Wall crack injection
Interior polyurethane crack injection with ports and surface seal.
- Category
- Crack repair
- Unit
- EA - Each
- Cost
- $145.00
- Default Price
- $395.00
- Margin
- 63.29%
- Markup
- 172.41%
- Updated
- Jul 9, 2026
- Internal
- Horizontal or structural cracks need estimator review before quoting.
CF-100 | Carbon fiber wall strap
Carbon fiber strap with prep, epoxy, and top/bottom anchoring as needed.
- Category
- Carbon fiber
- Unit
- EA - Each
- Cost
- $285.00
- Default Price
- $725.00
- Margin
- 60.69%
- Markup
- 154.39%
- Updated
- Jul 9, 2026
- Internal
- Engineer review may be required for severe movement.
SB-100 | Steel I-beam wall reinforcement
Steel I-beam reinforcement with base plate, bracket, and installation.
- Category
- Steel I-beams
- Unit
- EA - Each
- Cost
- $760.00
- Default Price
- $1,850.00
- Margin
- 58.92%
- Markup
- 143.42%
- Updated
- Jul 9, 2026
- Internal
- Confirm joist direction, slab condition, and beam height.
VB-100 | Vapor barrier installation
Wall or crawlspace vapor barrier material and standard fastening/sealing.
- Category
- Vapor barriers
- Unit
- SQFT - Square foot
- Cost
- $1.85
- Default Price
- $4.95
- Margin
- 62.63%
- Markup
- 167.57%
- Updated
- Jul 9, 2026
- Internal
- Add drainage matting or specialty fastening for uneven masonry.
BP-100 | Basement preparation allowance
Protection, dust control, contents movement allowance, and job setup.
- Category
- Basement preparation
- Unit
- FLAT - Flat rate
- Cost
- $285.00
- Default Price
- $650.00
- Margin
- 56.15%
- Markup
- 128.07%
- Updated
- Jul 9, 2026
- Internal
- Increase for finished basements or heavy contents.
CN-100 | Concrete removal and replacement
Concrete saw cut, removal, pour-back, and basic finish.
- Category
- Concrete removal/replacement
- Unit
- LF - Linear foot
- Cost
- $28.00
- Default Price
- $68.00
- Margin
- 58.82%
- Markup
- 142.86%
- Updated
- Jul 9, 2026
- Internal
- Use square-foot pricing for pads or wider removal.
LS-100 | Sewer/lift station support allowance
Lift station coordination and plumbing support allowance.
- Category
- Sewer/lift station support
- Unit
- ALLOW - Allowance
- Cost
- $950.00
- Default Price
- $2,200.00
- Margin
- 56.82%
- Markup
- 131.58%
- Updated
- Jul 9, 2026
- Internal
- Placeholder only; confirm with plumbing partner before final quote.
EL-100 | Electrical support allowance
Electrical support allowance for pump outlet, dedicated circuit, or alarm wiring.
- Category
- Electrical support
- Unit
- ALLOW - Allowance
- Cost
- $325.00
- Default Price
- $725.00
- Margin
- 55.17%
- Markup
- 123.08%
- Updated
- Jul 9, 2026
- Internal
- Confirm code requirements and electrician availability.
LB-100 | Crew labor
Crew labor for custom scope not covered by standard line items.
- Category
- Labor
- Unit
- HOUR - Hour
- Cost
- $55.00
- Default Price
- $115.00
- Margin
- 52.17%
- Markup
- 109.09%
- Updated
- Jul 9, 2026
- Internal
- Use for special conditions, callbacks, and custom prep.
EQ-100 | Equipment day
Daily mini excavator or specialty equipment allowance.
- Category
- Equipment
- Unit
- DAY - Day
- Cost
- $390.00
- Default Price
- $825.00
- Margin
- 52.73%
- Markup
- 111.54%
- Updated
- Jul 9, 2026
- Internal
- Delivery and fuel may require separate allowance.
DS-100 | Disposal/haul-off allowance
Dumpster, disposal, haul-off, and debris handling allowance.
- Category
- Disposal/haul-off
- Unit
- ALLOW - Allowance
- Cost
- $265.00
- Default Price
- $595.00
- Margin
- 55.46%
- Markup
- 124.53%
- Updated
- Jul 9, 2026
- Internal
- Increase for concrete-heavy jobs or limited dumpster access.
MS-100 | Miscellaneous allowance
Custom allowance for permits, restoration, or field-discovered scope.
- Category
- Miscellaneous
- Unit
- ALLOW - Allowance
- Cost
- $150.00
- Default Price
- $325.00
- Margin
- 53.85%
- Markup
- 116.67%
- Updated
- Jul 9, 2026
- Internal
- Use sparingly and replace with specific item when possible.